It took 72 men working 8hr a day to construct a wall 250 yard long,24 feet high and 6 feet wide how many men should be engaged for constructing a wall 275 yard long ,25 feet high and 9 feet wide if they work 9 hours a day and finish a work in same time as past.​

Answers

Answered by Jaytrivedi
10

(p1×t1)÷(work1)=(p2×t2)÷(work2)

(72×8)÷(250×24×6)= (p2×9)÷(275×25×9)

P2= 110 men

Answered by amamashu04
2

Answer:

110 mens would be required to construct a wall 275 yard long, 25 feet high and 9 feet wide if they work 9hr a day