John and David work on alternate days with John starting on the first day. John does 12.5% of the total work on the last day and finishes the work. If John alone can do the work in 6 days then which of following can be the number of days in which David alone can do the whole work? a) 24 days (b) 12 days (c) 8 days (d) 10 days
Answers
Answered by
10
Answer:
The answer is 8 days
Step-by-step explanation:
We can solve this by two methods
here i will explain both methods
- option method
let David can do it in 8 days
then
john. = 6 days
David. = 8 days
total work is 24 ( assume)
in a day work
john = 4
David = 3
one day john + one day john
4 + 3 = 7
7×3= 21
rest work is 24-21=3
which is. 3×100/24 = 12.5%
which is done by john
and this 12.5% is proving our answer.
2. Trick method
the work which was done by john on last day was 12.5%
John's one day work is
and he did only 12.5 % that means this is David's one day work share
so David's days
100/12.5= 8 days