John can do a piece of work in 60 days; he will do how much of the work in 40 days?
Answers
Answered by
1
Answer:
hi
your answer is here !
Step-by-step explanation:
In 1 day,
John does 1/60th of the work,
so in 40 days he will do 40 × 1/60 = 2/3rd of the work.