Math, asked by jasleenkaur71, 11 months ago

John does1/2 piece of work in 3 hours.
Joe does 1/4 of the remaining work in 1 hour
and George finishes remaining work in 5 hour.
How long would it have taken the tree working
together to do the work?​

Answers

Answered by sk940178
2

Answer:

\frac{30}{11} hours.

Step-by-step explanation:

Let us assume that the total work is W.

So, according to the given condition,

John takes 3 hours to complete \frac{W}{2} amounts of work.

John take 1 hour to complete \frac{W}{6} amounts of work.  .....(1)

Now, 1/4 th of the remaining work =\frac{1}{4}(W-\frac{W}{2})

                                                         =\frac{W}{8}

So, the condition gives that,

Joe takes 1 hour to complete \frac{W}{8} amounts of work.  .....(2)

Now, the remaining work =(W-\frac{W}{2}-\frac{W}{8})

                                          =(\frac{8-4-1}{8})W

                                           =\frac{3}{8}W

Again, by the condition,

George takes 5 hours to complete \frac{3}{8}W amounts of work.

George takes 1 hour to complete \frac{3}{40}W amounts of work.  .....(3)

Now, from statement (1),(2), and (3), when they all work together,

they will take 1 hour to complete (\frac{W}{6}+\frac{W}{8}+\frac{3W}{40}) amounts of work.

= (\frac{20+15+9}{120})W amounts of work.

=\frac{44}{120}W amounts of work.

=\frac{11}{30}W amounts of work.

Therefore, if they all work together W amounts of work will be done in

\frac{30}{11} hours.

(Answer)

Answered by wifilethbridge
3

Answer:

2.7 hours

Step-by-step explanation:

John can do part of work in 3 hours = \frac{1}{2}

Remaining work = 1- 1/2 = 1/2

Joe does 1/4 of the remaining work in 1 hour  

Joe does part of work in 1 hour = \frac{1}{4} \times \frac{1}{2}=\frac{1}{8}

Now remaining work = \frac{1}{2}-\frac{1}{8}=\frac{3}{8}

George  finishes remaining work in 5 hour.

George do part of work in 5 hours = \frac{3}{8}

George do part of work in 1 hour = \frac{3}{40}

John can do part of work in 1 hour = \frac{1}{6}

Together they can do part of work in 1 hour = \frac{1}{6}+\frac{3}{40}+\frac{1}{8}=\frac{11}{30}

So, they can do 11/30 part of work in hour = 1

They can do complete work in hour = \frac{30}{11}=2.7 hours

So, They can complete work together in 2.7 hours

Similar questions