John does1/2 piece of work in 3 hours.
Joe does 1/4 of the remaining work in 1 hour
and George finishes remaining work in 5 hour.
How long would it have taken the tree working
together to do the work?
Answers
Answer:
hours.
Step-by-step explanation:
Let us assume that the total work is W.
So, according to the given condition,
John takes 3 hours to complete amounts of work.
⇒John take 1 hour to complete amounts of work. .....(1)
Now, 1/4 th of the remaining work =
=
So, the condition gives that,
Joe takes 1 hour to complete amounts of work. .....(2)
Now, the remaining work =
=
=
Again, by the condition,
George takes 5 hours to complete amounts of work.
⇒George takes 1 hour to complete amounts of work. .....(3)
Now, from statement (1),(2), and (3), when they all work together,
they will take 1 hour to complete amounts of work.
= amounts of work.
= amounts of work.
= amounts of work.
Therefore, if they all work together W amounts of work will be done in
hours.
(Answer)
Answer:
2.7 hours
Step-by-step explanation:
John can do part of work in 3 hours =
Remaining work = 1- 1/2 = 1/2
Joe does 1/4 of the remaining work in 1 hour
Joe does part of work in 1 hour =
Now remaining work =
George finishes remaining work in 5 hour.
George do part of work in 5 hours =
George do part of work in 1 hour =
John can do part of work in 1 hour =
Together they can do part of work in 1 hour =
So, they can do 11/30 part of work in hour = 1
They can do complete work in hour =
So, They can complete work together in 2.7 hours