Let total  work be x

1 hour work of John =1/20

1 hour work of Peter = 1/25

1 hour work of john and peter=1/20+1/25

4 hour work of john and peter=4/20+4/25

=1/5+4/25

=9/25

work left after 4 hours=x - 9/25

time taken by peter to do the remaining work=( 9/25 )/(1/25)

=9/25 x 25/1

=9 hours