Jones Corp is evaluating a project that has the following annual free cash flows:
Period 00 11 22
Free Cash Flow -150−150 100100 150150
If the project's discount rate is 12\%12%, then what is the NPV of the project?
Answers
Answered by
0
Answer: 58.86
Explanation:
-150 + 100/1.12 + 100/1.12^2