Math, asked by vandanaxc277, 11 months ago

K can build a wall in 30 days. L can demolish that wall in 60 days. If K and L work on alternate days, when will the wall be completed ?
A) 120 days
B) 119 days
C) 118 days
D) 117 days

Answers

Answered by sanu1201
0
hey mate,
117 is the correct answer
Similar questions