Math, asked by sweetikumar, 9 months ago

Kailash joined Service
30th April, 2010
in a Company on
42 days
and
worked for
what
date
did
he
On
leave the job?​

Answers

Answered by rishabhpy3
6

Answer:

Hope it helps

Step-by-step explanation:

He left on 10th of June.

As he joined on 30th April so 41 days left.

Then may has 31 days so 10 days left and then till 10 June.

Answered by Tanyapreet
3

Answer:

I understand only some part but...

I can help u...

The answer is...

June 11,2010

If it help u please follow me...