Kapil can do 40% of the work in 10 days,
Sunil can do 1/5th of the same work in 5
days. In how many days can they together do
3/5th of the work?
Answers
Answered by
0
Answer:
both can do 3/5 th of the work in 15/2 or 7.5 days