karan can finish a task in 14 days, Smith can finish it in 17 days. Calculate how much time together they will take to complete the same job
Answers
Answered by
0
eska solution upper paper me hai.
send question for this number (6+3+9+5+7+1+6-4+1+2)
Attachments:
Answered by
1
Answer:
⇒ Karan and Smith can complete total work in days
Step-by-step explanation:
Given data
Karan can finish a task in 14 days
let x be the task
⇒ the work done by Karan in 1 day =
Smith can finish a task in 17 days
⇒ the work done by Smith in 1 day =
⇒ here we need find how much time will they take to complete the same job together
from given data
the work done by Karan and Smith together in 1 day =
= =
work can be done in 1 day
the total work x can be done in = = days
⇒ Karan and Smith can complete total work in days