Math, asked by asfaimtiaz340, 5 months ago

Kercise be
. If 360 workers can paint a shopping mall
in 96 days, how many days will 450
workers need?

Answers

Answered by samsingh6064
1

Step-by-step explanation:

60 days

hope you like it

Answered by abhiraj7813
1

Answer:

76.8 days

Step-by-step explanation:

1 workers = 96×360 days

450 workers = {96×360}÷450 days

450 workers = 384/5 days =76.8 days