Kishore can complete a work in 10 days, Nathan completes the same work in 15 days, How many days it will take if both work
together?
O 8 days
O 9 days
O 6 days
5 days
Answers
Answered by
0
Answer:
5 days.................
Answered by
6
Let us take the total work to be 30 units ( L.C.M of 10 , 15 )
Given , Kishore can complete a work in 10 days
i.e., 30 units of work in 10 days
⇒ 3 units of work per day by kishore.
Also , Nathan completes the same work in 15 days.
i.e., 30 units in 15 days.
⇒ 2 units of work by Nathan.
When both of them work together work done by them per day = ( 3 + 2 )
= 5 units / day.
so no. of days required now = ( Total work / work done per day )
⇒ Days = ( 30 / 5 ) = 6 days.
∴ Therefore both of them together takes 6 days to complete the same work.
Hope this helps you ✌️✌️☘️☘️.
Similar questions