Math, asked by sahii5099, 11 months ago

Kumar can complete 1/3 piece of work 4 days and ravi can do 1/6 same work in 3 days find the number of days work together complete

Answers

Answered by meetsachde9
9

Answer:

1.

1 day work of Kumar = 1/12

2.

1 day work of Ravi = 1/18

3.

1 day work of both = 1/12 + 1/18 = 5/36

4.

Time taken to complete the work by both of them = 36/5 days.

Similar questions