Math, asked by shaikhzain360, 4 months ago

Labor Information
-Regular Rate $16.00/hr
-Overtime Rate $24.00/hr
-Targeted Labor Cost $11,200/wk
-Labor Hours Needed 700/wk
-Any hour worked over 40 hrs/wk
must be paid overtime rate
For a 14-person team, how
does the actual weekly
labor cost compare to the
targeted labor cost?
$16 over target
$280 over target
$1120 over target
$2,440 over target
$5,600 over target

Answers

Answered by amitnrw
0

Given : Labor Information

-Regular Rate $16.00/hr

-Overtime Rate $24.00/hr

-Targeted Labor Cost $11,200/wk

-Labor Hours Needed 700/wk

-Any hour worked over 40 hrs/wk must be paid overtime rate

To Find : For a 14-person team, how does the actual weekly labor cost compare to the targeted labor cost?

$16 over target

$280 over target

$1120 over target

$2,440 over target

$5,600 over target

Solution:

Labor Hours Needed 700/wk

14-person team,   40 hrs/wk

= 14 * 40  = 560 hrs

Regular Rate $16.00/hr  

Hence 560 * 16  = 8960 $

remaining hours = 700 - 560 = 140$

Over time work = 140 $

Overtime Rate $24.00/hr

Hence 140 * 24  = 3360$

Total Cost = 8960 + 3360  =   12320 $

Targeted Labor Cost $11,200/wk

Hence 12320 - 11200  = 1120 $ / wk

Hence actual weekly labor cost compare to the targeted labor cost  $1120 over target

Learn More:

movie time

brainly.in/question/26768750

in a furniture shop 24 were bought at the rate of rupees per table the ...

brainly.in/question/7645308

What is the percentage of gold present in 'Hallmark' gold? (Answer ...

brainly.in/question/4634338

Answered by 1hk17ec069
0

Answer:

for 14 person team how does the actual weakly labour cost comap

Similar questions