Accountancy, asked by kukucgr142, 13 hours ago

Labour Information


– Regular Rate £15.00/hr
– Overtime Rate £22.50/hr
– Targeted Labour Cost £12,000/wk
– Labour Hours Needed 800/wk
– Any hour worked over 40 hrs/wk must be paid overtime rate



Question
For a 13-person team, how many extra workers should be hired to meet the labour hours needed without overtime?

Answers

Answered by Sanjanasingh76076190
4

Answer:

A short ex

Normal working rate =

R

s

.

x

and Overtime working rate =

R

s

.

2

x

Total no. of working hours =

20

Overtime working hrs =

y

Normal working hrs =

(

20

y

)

hrs

Total earned

E

=

(

20

y

)

x

+

2

x

(

y

)

=

x

(

20

y

)

+

2

x

y

Answered by SteffiPaul
4

Therefore the number of extra workers who should be hired is 10 workers.

Given:

Labor information,

Regular Rate = £15.00/hr

– Overtime Rate = £22.50/hr

– Targeted Labour Cost = £12,000/wk

– Labour Hours Needed = 800/wk

– Any Labor worked over 40 hrs/wk must be paid overtime rate

To Find:

Number of persons in the team = 13 persons

Several extra workers should be hired to meet the labor hours needed without overtime.

Solution:

The given question can be solved as shown below.

Labour Hours Needed = 800/wk

But the team consists of 13 people and one labor can work for 40 hrs/wk without any overtime.

So Labour hours of 13 person team without overtime = 13 × 40 = 420 hrs/wk

Remaining labor hours needed to attain the task = Labour Hours needed - labor hours of 13 person team

⇒ Remaining labor hours needed to attain the task = 800 - 420 = 380.

Now we need extra men to work for 380 hrs/wk

So the number of extra men required = ( Remaining labor hours needed ) / ( Work hour of a single person without overtime )

⇒ The extra men required = 380 / 40 = 9.5 ≅ 10

Therefore the number of extra workers who should be hired is 10 workers.

#SPJ2

Similar questions