Leena can complete a work in 12 days. What amount of work can she do in 9 days
Answers
Answered by
1
Answer:
leela can do 3/4th of her work in 9 days
Step-by-step explanation:
let the total work is x
so work done / day = x/12
now , in 9 days , the work done = 9x/12 = 3x/4
so, leela can do 3/4th of her work in 9 days.
Answered by
0
Answer:
3/4
Step-by-step explanation:
12 days to complete 1 work
1 day to complete= 1/12
9 days to complete (1/12)×9 = 3/4