Let 100 worker can finish the task in 50 days. 100 worker started completing the task by working for 10 days. Now to finish the task as soon as possible 100 more workers are employed. Now calculate the total number of days required to complete the task.
Answers
Answered by
1
Answer:
100 workers can finish the task in 50 days
Therefore, total work is = 50*100 men days
To complete the task in 30 days, no of men required = 50*100/30
=166.66
Hence men can't be in fraction
Therefore, no of men required = 167
Step-by-step explanation:
HOPE IT HELPS YOU !
PLZ MARK ME AS BRAINLIEST
THANK YOU
Answered by
0
Step-by-step explanation:
100 workers can finish the task in 50 days
Therefore, total work is = 50*100 men days
To complete the task in 30 days, no of men required = 50*100/30
=166.66
Hence men can't be in fraction
Therefore, no of men required = 167