Let 100 worker can finish the task in 50 days. 100 worker started completing the task by working for 10 days. Now to finish the task as soon as possible 100 more workers are employed. Now calculate the total number of days required to complete the task.​

Answers

Answered by 57pranavdmandre
1

Answer:

100 workers can finish the task in 50 days

Therefore, total work is = 50*100 men days

To complete the task in 30 days, no of men required = 50*100/30

=166.66

Hence men can't be in fraction

Therefore, no of men required = 167

Step-by-step explanation:

HOPE IT HELPS YOU !

PLZ MARK ME AS BRAINLIEST

THANK YOU

Answered by srujanasesetty261988
0

Step-by-step explanation:

100 workers can finish the task in 50 days

Therefore, total work is = 50*100 men days

To complete the task in 30 days, no of men required = 50*100/30

=166.66

Hence men can't be in fraction

Therefore, no of men required = 167