Math, asked by farhankaimuri403, 8 hours ago

Let N men be able to finish a piece of work in 40 days. If there were 8 more men then the work would be finished in 20 days less. Calculate the original number of men?

Answers

Answered by anilshinde2401
1

Answer: 8 mens

Step-by-step explanation:

If orig men=8. Can complete a work in 40 days ,

additional 8 mens

Total mens =16

1/40 -1/20=first 8men days+additional 8mens work days

1/20=1/40+1/40=2/40

1/20=1/20

Means originally there were 8 mens

Final ans =8 mens