Math, asked by xonzow, 9 months ago

Let's solve thisA can finish the work in 16 days while B can finish the work in 8 days.After A started the work alone,B joined him after 4 days.Find out the total time taken to finish the work.​

Answers

Answered by Anonymous
0

Answer:

8 days..

Step-by-step explanation:

A's 1 day work = 1/16

B's 1 day work = 1/12

(As A worked for 2 days alone we'll find work done by A in 2 days by multiplying his one day work by 2)

A's 2 day work = 2x(1/16) =1/8

Remaining work = 1–1/8 =7/8

( Total work is always presumed to be 1 in all such cases )

Now this remaining work will be done by A and B together .

(A+B)'s 1 day work = (1/16) + (1/12) = 7/48

A and B together can do the remaining work in = (7/8)÷(7/48) = 6 days

Total time taken = 6+2 = 8 days

hope this helps you.. plzz Mark as BRAINLIEST answer

Answered by chanchalmehra09
0

Answer:

Let whole work be W.

Work done by A in one day = W/16

Work is done by B in one day = W/12

A worked for 2 days=2×4/16

=W/8

A and B worked for x days(let)

w/8+x(w/16+w/12)=w

x×7/48=7/8

⇒x=6 days.

Hence, the answer is 6 days.

Similar questions