लगाउनुहोस्। A and B can do a piece of work in 18 days and 24 days respectively. A and B both worked together and after some days A left the work. B finished the remaining work in 3 days. How long did A worked with B? Find it.
Answers
Answered by
1
Step-by-step explanation:
16 days
(A + B)’s 1 day’s work $latex = \frac{1}{18}&s=1$
(B + C)’s 1 day’s work $latex = \frac{1}{24}&s=1$
(C + A)’s 1 day’s work $latex = \frac{1}{36}&s=1$
On adding,
2(A + B + C)’s 1 day’s work $latex = \frac{1}{18}+\frac{1}{24}+\frac{1}{36} = \frac{4+3+2}{72} = \frac{1}{8}&s=1$
∴ (A + B + C)’s 1 day’s work $latex = \frac{1}{16}&s=1$
∴ A, B and C together will complete the work in 16 days.
Hence option [D] is correct answer.