Math, asked by kawalb9026, 10 months ago

Machine a can do a certain job in 12 days working 2 full shifts while machine b can do the same job in 15 days working 2 full shifts. If each day machine a is working during the first shift, machine b is working during the second shift and both machines a and b are working

Answers

Answered by bharat9291
0
in one shift A can complete the job = 24 days
in one shift B can complete the job = 30 days
in 1 day A work ,working 1 shift = 1/24
in 1 day B work ,working one shift = 1/30
total work done by both in 1 day =( 1/24 )+ (1/30) = 54/720 = 3/40
work can be completed in = 40/3 days
Similar questions