Madhu and Meena can do a piece of work in 9 hours. Meena and Mamta can do it 12 hours and Madhu and Mamta can do it in 18 hours. in how many hours will they will finish the work together and separately?
Answers
Answered by
1
Answer:
All together = 8 hrs
Madhu = 24 hrs
Meena = 14.4 hrs
Mamta = 72 hrs
Step-by-step explanation:
Madhu = A
Meena = B
Mamta = C
1/9 = 1/A + 1/B
1/12 = 1/B + 1/C
1/18 = 1/A + 1/C
Adding all
1/9 + 1/12 + 1/18 = 2 (1/A + 1/B + 1/C)
4 + 3 + 2 = 36*2 (1/A + 1/B + 1/C)
9/72 = (1/A + 1/B + 1/C)
1/8 = 1/A + 1/B + 1/C
So all together can do in 8 Hrs
1/C = 1/8 - 1/9 = 1/72 so C = 72 hrs
1/B = 1/8 - 1/18 = 5/72 so B = 72/5 = 14.4 Hrs
1/A = 1/8 - 1/12 = 1/24 so A = 24 Hrs
Please mark the answer as "The Brainliest answer" if you like it
Answered by
1
Hey mate here's the answer of your question
Attachments: