Madhuri, a government contacter,
has a work force of 560 Men
who can finish a certain piece
o work in 8 months. How many
extra men must he employ
I to complete the job in
7 months ?
Answers
Answered by
0
Extra 80 men will be employed to complete the work in 7 months.
Explanation :
Given that,
Men
Time months months
Work
Time months
Men
Extra men ?
We know that,
the formula
So extra 80 men will be employed to complete the work in 7 months.