Math, asked by mohdtaufiq31878, 1 year ago

Man A finishes a work in 18 days and Man B can do the same in half the time taken by A. Then working together, What part of the same work they can finish in a day?
(A) 1/9
(B) 2/5
(C) 2/7
(D) 1/6
Please give quick response....

Answers

Answered by satyam9027
2
(D) 1/6
1/9+1/18=1/6
hope this helps you