Man Mohan can alone do a work in 16 hours and Brij Mohan alone in 24 hours.
With the help of Munnilal they all the three can finish the work in 6 hours only.
How long will Munnilal take to do the work independently?
Answers
Answer:
This photo is answer to your
pls mark me branliest
Answer: 16 Hours time will be taken by Munnilal in order to do the work independently.
Given : ManMohan can alone do a work in 16 hours and Brij Mohan alone in 24 hours.
To Find : Munnilal time taken to do the work independently .
Step-by-step explanation:
In order to find the time taken by Munnilal we need to find the work done by each indiviual person in one hours .
Whenever any work is done, the total work itself can be taken as a whole. Therefore, we assume the total work done as one unit in the problems we encounter to simplify calculations. In other words, R and T are inversely proportional as RT = W, which is a fixed quantity.
Work done by ManMohan in one hour =
Work done by BrijMohan in one hour =
Let the work done by Munnilal in one hour be =
Then, Work done by all worker in one hour is
(Given that if all work together the time taken will be 6 hours)
Hence Munnilal will take 16 hours if he work alone .
45 men working 8 hours a day can finish a project within a given time. five men are unable to report for the work how long should be rest work a day to finish the project on time
https://brainly.in/question/4275281?msp_srt_exp=4
If 3 men van plough a field in 9 days, how long will 4 mens take such that all men work at same time plzz with method
https://brainly.in/question/32025337?msp_srt_exp=4
#SPJ3