Manish completes a work in 20 days. After 8 days Sriram joined the work. In how many days will the work be completed ?
Statements :
I. Sriram takes twice the time than Manish to complete the work.
II. Sriram completes half the work in 15 days.
A) Statement I alone is sufficient to answer the question
B) Statement II alone is sufficient to answer the question
C) Either the statements I & II is sufficient to answer the question
D) Neither the statements I & II is sufficient to answer the question
Answers
Answered by
1
Hay mate here is your answer ✌❤☺
option C is Correct
Hope it will help you ☺❤
option C is Correct
Hope it will help you ☺❤
Answered by
2
Manish completes a work in 20 days. After 8 days Sriram joined the work. In how many days will the work be completed ?
Statements :
I. Sriram takes twice the time than Manish to complete the work.
II. Sriram completes half the work in 15 days.
A) Statement I alone is sufficient to answer the question
B) Statement II alone is sufficient to answer the question
C) Either the statements I & II is sufficient to answer the question
D) Neither the statements I & II is sufficient to answer the question
Answer: C) Either the statements I & II is sufficient to answer the question
Read Description:
From statement I,
Time taken by Sriram to complete the work = 40 days
From statement II,
Time taken by Sriram to complete the wok = 30 days
So from both either by statement I or statement II we can find the time to complete the work.