Math, asked by shuklamayank62, 11 months ago

Mayank can do a piece of work in 10 days , sushil can do the same work in 12 days Mayank ,sushil and mohan in 4 days.In how many days will mohan complete the work alone?​

Answers

Answered by RvChaudharY50
29

Answer:

lcm 0f 10,12 and 4 = 60

efficiency = 6, 5, 15

than efficiency of mohan = (15-6-5) = 4 unit

days he will take to complete whole work = 60/4 = 15 days (Ans)

(mark as brainlist)

Answered by vanshika814441
0

Answer:

2 is the correct answer as mayank work -suehil workk=12-10 =2

Similar questions