Meera completed her work in 60 days . How much part of the work will she complete in 45 days. In how many days will she complete 3/5 part of the work.​

Answers

Answered by harikaran9788
1

Step-by-step explanation:

Meera completed her work in 60 days,

some part of the work will she complete in 45 days

we have to find the work,

take LCM for 60 & 45 = 180 total work

capacity = work/time

= 180/60

= 3 units

some part of work she complete in 45 days ,

w = c*t

= 3 * 45

= 135 work will be completed in 45 days

135/180 = 3/4th of the work is completed in 45 days

In how many days will she complete 3/5 part of the work.

180*3/5 = 108 work

T = w/c = 108/3= 36 days