Math, asked by ashokaituc7068, 1 year ago

Men and boy can do a work together in 24 days. if the men alone wirk for the last 6 days then it is completed in 26 days. hiw long wilk the boy alone take ti complete the work

Answers

Answered by aishowrya
5
Heya!

Time taken if the man and boy work together to complete the work = 24 days

Their 1 day work = 1/24

ATQ, for the last six days, man alone does the work then it is completed in 26 days.

So, man and boy work together for 20 days.

man and boy's 20 days work
= 20 × 1/24
= 20/24
= 5/6

Remaining work = 1 - 5/6 = 1/6

Then, 1/6 of work is completed by a man in 6 days.

i.e man's 1 day work = 1/36

1/36 + boy's 1 day work = 1/24

Boy's 1 day work = 1/24 - 1/36 = 1/72.

∴ the boy alone can complete the work in 72 days.

Hope it helps! ^^
Similar questions