method
Find all the sequences that minimize the
total elapsed time required to complete the
following tasks on two machines :
Task
A B C D E F
Machine I.
4 10 8 18 12 14
Machine II:
12 16 14 8 6 6
Also find the idle time for both the
machines.​

Answers

Answered by rohanpaunikar704
0

Answer:

Total Elapsed time) Total elapsed time is the time required to complete the jobs from start of first job t of last job in a sequence. Definition 3: (Idle time) Idle time is the time when there job to process on a machine