Micro & Chip Inc. receives a large order of components that needs to be fulfilled in 15 days. It takes 300 days for 2 employees to prepare the order for dispatch.
How many employees are needed to complete the work in 1/20 of that time, that is, in 15 days?
Answers
Answered by
0
Answer:
need 10 employees
Step-by-step explanation:
300: 2 :: 15 : ?
300*? % 15*2
300%30
= 10 employes
I answered using inverse proportion
mark me as brainlist