Mohan and Rohan can do a piece of work in 12 days Rohan alone can finish in 30 days.In how many days can Mohan alone finish the work and the answer of this question is 20 days
Answers
The work done by Mohan alone is in 20 days .
Step-by-step explanation:
Given as :
Mohan and Rohan can do a piece of work in 12 days
Rohan alone can finish in 30 days
Let The work done by Mohan alone in = x days
According to question
One day work of Mohan and Rohan together =
One day work of Rohan alone =
So, One day work of Mohan alone =
Now,
Mohan and Rohan together 1 day work = Rohan's 1 day work + Mohan's 1 day work
i.e = +
or, = -
or, =
Or, =
∴ =
i.e x = 20
So, The work done by Mohan alone in = x = 20 days
Hence, The work done by Mohan alone is in 20 days . Answer
Answer:
20days
Step-by-step explanation:
Given as :
Mohan and Rohan can do a piece of work in 12 days
Rohan alone can finish in 30 days
Let The work done by Mohan alone in = x days
According to question
One day work of Mohan and Rohan together = \dfrac{1}{12}
12
1
One day work of Rohan alone = \dfrac{1}{30}
30
1
So, One day work of Mohan alone = \dfrac{1}{x}
x
1
Now,
Mohan and Rohan together 1 day work = Rohan's 1 day work + Mohan's 1 day work
i.e \dfrac{1}{12}
12
1
= \dfrac{1}{30}
30
1
+ \dfrac{1}{x}
x
1
or, \dfrac{1}{x}
x
1
= \dfrac{1}{12}
12
1
- \dfrac{1}{30}
30
1
or, \dfrac{1}{x}
x
1
= \dfrac{5-2}{60}
60
5−2
Or, \dfrac{1}{x}
x
1
= \dfrac{3}{60}
60
3
∴ \dfrac{1}{x}
x
1
= \dfrac{1}{20}
20
1
i.e x = 20
So, The work done by Mohan alone in = x = 20 days
Hence, The work done by Mohan alone is in 20 days . Answer