Math, asked by momdad212001, 4 months ago

Mohan can do 1/5 of piece of work in 10 days in how many days will he do the remaining work​

Answers

Answered by diyahashtag
1

Answer:

40 more days to complete the rest of the work

Step-by-step explanation: