Math, asked by shivanitamrakar, 10 months ago

Mohan can do a certain job in 16 days. Sohan is 20% more efficient than Mohan. How many days does Sohan alone

take to do the same job?​

Answers

Answered by arnavsaini98
2

Mohan can do in :16 days

sohan can do it in :16-(20/100*16)

=16-3.2

=13 days (approx)

Similar questions