mohan did 1/2 of the work on monday and 1/3 of the work on the tuesday . how much work will he have to do on Wednesday to complete the remaining work?
Answers
Answered by
3
Answer:
what type of answers do you want
Answered by
7
Let 1 be the whole work the remaining work=1-1/2-1/3=1/6