Mohan does 25% more work than sohan. If Sohan can do it in 20 days, then
(a) In how much days will mohan alone finish the work? (b) working together
in how many days Mohan and Sohan will finish it?
Answers
Answered by
1
Answer:
A's 1 day's work =
25
1
Similarly, B's 1 day's work =
20
1
A's and B's together 1 day's work
25
1
+
20
1
=
100
4
+
100
5
=
100
4+5
=
100
9
Their 5 day's work together = 5 x 1 day's work
1−
100
45
=
100
100
−
100
45
=
100
100−45
=
100
55
Now, this remaining work is done by B.
Let B takes x days to complete it.
20
1
×x=
100
55
⇒x=
100
55
×20
⇒x=
5
55
⇒x=11
Hence, B will finish the remaining work in 11 days.