Mohan does a work alone in 3 days and Sohan does the same work alone in 6 days In how many days will Mohan and Sohan together complete that work​

Answers

Answered by asmita7766
0

Answer:

9

Step-by-step explanation:

We have to add 3 to 6 as they both have down and they are asking if they worked together how much time will they take. We added the time consumed by both.

Answered by amkumar2005
0

Answer:

Mohan's single day work=1/3

sohan's single day work=1/6

both of their work together one day=1/3+1/6

1/3+1/6=1/2

so if they come together the can complete the work in 2 days