Mohan takes 16 days less than manoj
to do a piece of work. If both working
together can de in 15 days How many days mohan can complete the work alone
Answers
Answered by
2
Answer:
it is given that they both can do the work in 15 days
since the number of days are not negative
so,x=24
thus mohan alone can complete the work in 24 days
Step-by-step explanation:
I think it helps you bro