Mr. X has to build a wall 1000 meters long in 50 days. He employs 56 men but at the end of 27 days finds that only 448 meters are built. How many more men must be employed so that the work may be finished in time?
Answers
Answered by
10
56 men working for 27 days completes 448 meters
1 men working for 27 days completes (448/56) = 8 meters
1 men working for 1 day completes (8/27) meters
Remaining work = 1000 - 448 = 552 meters
Remaining days = 50 - 27 = 23 days
1 men working for 23 days complete (8/27) × 23 = 184/27 meters
No of men required to complete 552 meters in 23 days = 552 ÷ 184/27
= (552 × 27) / 184 = 81 mens
56 men are already working
so number of more men require = 81 -56 = 25
hence 25 more men needs to be employed to finish work in 50 days