much time will the leak take to empty the tank?
Long Answer Questions
8. 2 men each working 5 hours per day can finish painting a house in 12 days. How long will 4 men each working,
2 hours per day take to finish the same job?
Lari and Ganesh can plough a field in 1 day and 15 dren izoly They both work together for 5 days
Answers
Answered by
2
Step-by-step explanation:
1) let the number of days be x
the ratio of days is ,
12:x = 4×2:2×5
12:x = 8:10
12. = 8
x =10
x=12×10/8
x= 120/8
x= 15
4 men each working will take 15 days to complete the work.