Multiple choice question(MCQs): iii) If 20 men can complete a work in 8 days then 10 men can complete half of that work in option a) 32 days b) 8 days c) unchanged d) triple.​

Answers

Answered by vaibhavdhankhar10
1

Step-by-step explanation:

khud solve karke dekhiye plz

its your fayda not ours

Answered by dineshk19
2

Answer:

time*men\work=time*men/w

8*10/w=10*days/w/2

80/w=20*days/w

days= 8

hope it will help

enjoy