Name the various material variances.
Answers
Answered by
9
a) Material Cost Variance (MCV):
It is the difference between the standard cost of materials allowed (as per standards laid down) for the output achieved and the actual cost of materials used. Or Material Cost Variance = Material Price Variance + Material Mix Variance + Material Yield Variance.
HOPE IT HELPS!!!!!
PLEASE MARK ME AS BRAINLYEST. You will get 3 points.
Answered by
3
Explanation:
(a) Material Cost Variance (MCV):
It is the difference between the standard cost of materials allowed (as per standards laid down) for the output achieved and the actual cost of materials used. Or Material Cost Variance = Material Price Variance + Material Mix Variance + Material Yield Variance