naresha can work in 50 days dinesh complete in 45 days if he work with naresha. dinesh does in 90days how long will naresh do the work?​

Answers

Answered by amitnrw
0

Given : naresha can work in 50 days. dinesh complete in 45 days if he work with naresha  .

To find : if Dinesh work  for 90 days , how long will naresh has to work

Solution:

naresh  can work in 50 days

=> Naresh 1  Day work  = 1/50

Dinesh Completes in 45 Days    iof he work with naresh

=> Dinesh 1 day work  = 1/45  - 1/50

=>  Dinesh 1 day work  = (10 - 9)/450  = 1/450

=> Dinesh alone complete in 450 days

Work done by Dinesh in 90 days =  90/450  = 1/5

(1/5) work done by Naresh in  (1/5)50  =  10 Day

Number of Days taken by Naresh to do remaining work  =  50- 10   =  40 Days

Naresh will work for 40 Days to complete work

& Naresh will do work in 10 days what Dinesh do in 90 days

Learn more:

A and B can do a piece of work in 12 days; A,B and C all working ...

https://brainly.in/question/7839397

A takes 6 days less than B to do a work . If both A and B working ...

https://brainly.in/question/7656573

Similar questions