Nazim and Manoj together can finish a work in 8 days. Both together started the work. After 3 days Nazim fell ill. Manoj alone can finish the remaining work in 15 days. How many days would Nazim take to finish that work alone.
Answers
Answered by
0
Answer:
Nazim+manoj one day work.
= 1/8
3 days work = 3/8
Balance work=l-3/8=2/8
Let manoj's 1 day work be1/x
2/8 xX/1=15
2x/8=15
2x = 120
x = 120/2 = 60,
Ans.60 days
=
=