Math, asked by SupriyaPandit, 5 months ago

Neeraj can do a piece of work in 10 days , Aman can do the same work in 12 days. Neeraj, Aman and Virat together finish the same work in 4 days. In how many days will Virat complete the work alone?
Plz give the answer fastly.​

Answers

Answered by JaiJinendra
1

Answer:

Virat completed the work alone in 15 days.

Step-by-step explanation:

let , Neeraj =x ,Aman=y and Virat be z

  • for solving this type of questions : formula is :. xyz/xy+yz+xz = together work of x,y,z.

  • 10×12×z ÷10×12+12×z+10×z
  • 120×z ÷120+12z+10z
  • 120×z / 120 + 22z
  • v/120+22z =4/120
  • 120z=480+88z
  • 480 = 120z-88z

=32z

  • 480/32= Z
  • z=15

so,

Virat complete the work alone in = 15 days .