Math, asked by bhaktiawasthi777, 1 month ago

Neha can complete a job in 12 days and mahima can complete the same job in 16 days. they both start working on the job. after 6 days, neha leaves. how many more days will mahima take to complete the remaining job?​

Answers

Answered by ranjeetkumar21199
1

Answer:

2 days

Step-by-step explanation:

?????????????????

Attachments:
Similar questions