Nep 1 :
24 men working at 8 hours per day can do a piece of work in 15 days. In how many du :
can 20 men working at 9 hours per day do the same work?
175 men can dio a canal 1150
4.​

Answers

Answered by SUMANTHTHEGREAT
4

24 men working 8 hrs / day can do a piece in 15

days

∴ Total work units =24×8×15

=2880

No.of days required by 20 men, working at

a hrs/day= 2880/(20×9)

=16 days

hope this helps you