Nimai and Gaurang can complete a piece of work in 40 days and 60 days respectively.With Nityanand's help they completed the work in 10 days.If the total contract amount for completing the work is ₹4800.What is Nityanand's share? Please show explanation
Answers
Answered by
0
Answer:
2800
Step-by-step explanation:
please follow me
the ratio is 3:2:7
so the Nityananda get 7/12into4800
2800