Nirmit can do 2/3 of a job in 18 days. Kashish is twice as efficient as Nirmit. In how many days Kashish will complete the job?

A) 29/4 B) 27/2 C) 31/2 D) 13/2

Answers

Answered by ayu3095
0

Answer:

29/4____________________