Math, asked by artigupta1743, 6 months ago

nitin can do a piece of work in 24 days while Raman can do it in 30 days. In how
many days can they complete it, if they work together?

Answer is 40 by 3 days

Answer me fast please ​

Answers

Answered by bhagyashreechowdhury
1

Given:

Nitin can do a piece of work in 24 days

Raman can do it in 30 days

To find:

In how  many days can they complete it, if they work together?

Solution:

Nitin alone can do a piece of work in 24 days

So, in 1 day, Nitin can do = \frac{1}{24}

Raman alone can do the piece of work in 30 days

So, in 1 day, Raman can do = \frac{1}{30}

Now,

In 1 day, both Nitin and Raman can complete,

=  \frac{1}{24} + \frac{1}{30}

= \frac{5\: + \:4}{120}

= \frac{9}{120}

∴ Both Nitin & Raman can complete the work in = \frac{120}{9} = \frac{40}{3} \:days =\bold{ 13.33 \:days}

Thus, if they work together, then Nitin and Raman will complete the work in 13.33 days.

-------------------------------------------------------------------------------

Also View:

A takes 10 days less than the time taken by B to finish a piece of work.

If both A and B together can finish the work in 12 days, find the time

taken by B to finish the work.​

https://brainly.in/question/27372352

Deepak can do a work in 18 days he works alone for 6 days and Mohit alone finish the remaining work in 24 days both of them working together can complete in the same work in how many days​?

https://brainly.in/question/14702091

A can do a piece of work in 9 days.  B can do the same piece of work in 10 days.  C can do the same piece of work in 15 days.  B and C start working and left after 2 days.  In how many days remaining  work will be finished by A?

https://brainly.in/question/14878274

A and B can do a work in 34/3  days working alternatively with B working first. A can  complete work alone in 48 days. In how many days B does 4 times of the work?

https://brainly.in/question/10367778

Answered by nehasaxena6976
0

Answer:

the both finish the work in 40/3 days